Before starting any work on site, review the existing site's switchboard layout:
- Identify existing supply voltage to switchboard
- Identify any controlled loads on site and whether these are already monitored by an existing current transformer/s
- Identify the number of Solar Analytics meter/s that need to be replaced
- Identify existing solar system/s details (if possible)
- Identify if any additional loads are to be monitored and ensure additional current transformers are provided. Examples include:
- Off Peak Controlled Loads like hot water services and underfloor heating
- Air Conditioning
- Electric Vehicle charging station
- Pool pumps and spa's
- Document current transformer circuit allocations for each meter on the current transformer circuit diagram (Link to PDF)
Begin Installation work:
- Isolate all sources of power supply to the switchboard (Grid, Solar, Battery etc)
- Test and confirm dead
- Remove the voltage & current transformer terminal blocks from the Solar Analytics meter and remove the meter from the DIN rail
- Add any additional current transformers to the current terminal block as per the current transformer circuit diagram
- Connect the voltage and current terminal blocks to the Clipsal Cortex meter
- Install the Clipsal Cortex meter onto the DIN Rail
- Repeat steps 3. to 6. for any additional meters to be replaced
- Turn on all power supplies to the switchboard including the Clipsal Cortex meter
Commission the new Clipsal Cortex Meter:
Getting started with Clipsal Cortex Fleet app
Commissioning using the Clipsal Cortex Fleet app